Construction update

Piling and foundation work is well underway on the Sidewinder Production Facility. The separators, exchanger and coalescer are being built and tested in a shop in town, then we ship everything out to the site to weld it together. At the same time we’re building the 8” pipeline from the actual Sidewinder site about 3.3km’s away to tie into a major gas pipeline. When we attach the pipeline to the plant, we’ll be ready to produce.

 

We have a little more than 1700 m of our pipeline in the ground, and are on our way up the easy portion of the track to the Vector tie-in point.

We have a little more than 1700 m of our pipeline in the ground, and are on our way up the easy portion of the track to the Vector tie-in point.

4-and-8-inch-strung-and-welded1
piling-for-tankfarm2

The facility piling goes in, and in town, we run the gas coalescer hydrotest.

gas-coalescer-hydrotest